Study for the PRINCE2 Foundation Exam. Explore interactive flashcards and multiple-choice questions, with detailed hints and explanations. Be well-prepared for your certification!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


From which role's perspective does the Managing Product Delivery process primarily view the project?

  1. Project Manager

  2. Team Manager

  3. Stakeholder

  4. Executive

The correct answer is: Team Manager

The Managing Product Delivery process in PRINCE2 primarily focuses on the role of the Team Manager. This process is concerned with ensuring that the planned products are delivered effectively and efficiently by the project team. The Team Manager is responsible for managing the people who are producing the project deliverables, ensuring that they understand the work required and have the resources needed to complete their tasks. From the Team Manager’s perspective, the emphasis is placed on the day-to-day delivery of products, monitoring progress, and managing team dynamics. This role translates the project plans and requirements into actionable tasks for the team, coordinating activities, and addressing any issues that arise during the development of the products. In contrast, other roles such as the Project Manager, Stakeholder, or Executive focus more broadly on the overall management and strategic oversight of the project rather than on the specifics of how the actual product delivery is managed on the ground.